Hello Experts,
I have one issue while displaying the Report of S_ALR_87013558
Issue:
Example: I have Project Definition: Over all Budget is 100
But we returned Budget is 80
Now the current budget is 20.
In the Report in the object category , Over all budget is displaying 20 instead of 100.( In the highlighted with blue budget over all it should show 100 instead of 20)
If i want to see over all budget as 100 in object category what i need to change the settings.
Can anyone guide me? how to see report in that way